Nexus Manufacturing
Manufacturing Dashboard

Perth, Australia (Minerals) Details

← Back to Nexus Minerals Dashboard

Visualizations

full-site diagram for Perth, Australia (Minerals)
Full Site System Summary

System Data

Not available

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Nullam in dui mauris. Vivamus hendrerit arcu sed erat molestie vehicula.

IncludedProjectDeploy DateEnergy Savings (MMBtu/yr)Electricity Increase (kWh/yr)Capital CostCarbon Savings (MT/yr)Annual Cost SavingsROI (years)
Heat Recovery Steam Generator (HRSG) and Condensing Economizer132,00007,260$708,8402.1 years
Kiln Insulation and Partial Electrification144,3754,230,1887,941$487,6411.0 years
Pre-Dryer MVR Concentrator226,87516,785,23012,478$76,92332.5 years
Dryer Exhaust Hot Water Generator33,00001,815$177,2106.8 years
Dryer Electrification with Thermal Storage61,8752,702,2633,403$148,51510.1 years
Full Kiln Electrification with Thermal Storage226,87513,898,45212,478$273,22418.3 years
Total825,000$12,200,00045,375$1,872,3536.5 years